SAP parameters DRP

EMPEZAR

Índice

Selecciona lo que estés buscando

MRP views

Material Master

MRP areas-views

Material Master, MM02 and MRP views

MRP Views

Material Master

Material Master

  • Material master is the most important master data in SAP MM and in fact for the whole logistics area.
  • Material master holds data about material characteristics, material type, department information,material batch, and so on.

Change or modify a material

Siguiente

MRP VIEWS

MRP3

MRP4

MRP2

MRP1

MRP1 view DRP parameters

Siguiente

MRP2 view DRP parameters

10

11

Siguiente

12

MRP3 view DRP parameters

13

Siguiente

MRP4 view DRP parameters

14

Siguiente

MRP Areas - Views

MRP AREAS

MRP2

MRP1

MRP Forecast View

MRP AREAS

Siguiente

MRP Areas MRP1 View

Siguiente

MRP Areas MRP2 View

Siguiente

MRP Areas - MRP Forecast View

Siguiente

1. In transaction MM02 (Change) on MRP1. We have the MRP Areas button that show the next views

  • MRP 1
  • MRP2
  • FORECAST
  • Consumption Values

1. In transaction MM02 (Change) on MRP1. We have the MRP Areas button that show the next views

  • MRP 1
  • MRP2
  • FORECAST
  • Consumption Values

9. Schedule Margin key

Mandatory field. Keep ‘000’ as a default value.

In transaction MM02 (Change) in SAP, there are 4 MRP views

  • MRP1, MRP2, MRP3 and MRP4.
MRP views allow the production staff to enter the basic data required for the production of this material specific to the plant.

3. MRP Controller

  • Reflects a person who is responsible for the planning of the material in one plant or company.
  • Any planned material should be assigned to a MRP controller.
  • Standard SAP reports will filter materials and results based on MRP controllers.

3. Lot size

Determines the procedure to calculates the reorder quantity in the planning run.

a) Static lot sizes

Determines a static lot sizing. The most common options are:

EX – Any requirement will trigger the exact quantity to be produced or purchased

FX and HB – not used in Becle

b) Lot sizes by period procedure

SAP will consolidate the requirements in a given period and manage them as the batch size to be produced or purchased. The most common options are:

WB – Weekly lot size

W6 – 42 days lot size

W2 – 14 days lot size

W9 – 60 days lot size

W3 – 21 days lot size

WQ – 91 days lot size

W4 – 28 days lot size

YS – 180 days lot size

6. Special procurement

This field helps to define any special procurement process involved in the procurement of the material. The special procurement type is only set on the receiving plant.

14. Follow-up material

This is the material number of the material that will take the place of the discontinued material on the effective-out date. The replacement material must exist in SAP, have the same unit of measure and be planned in the MRP This functionality is only for BOM components, it doesn’t work with finished goods.

13. Strategy group

Is a field that groups planning strategies. In Becle ‘CC’ value is used, and it represents a make to stock strategy.

1. Plant-Specific material status

The field in this screen defines the material status at the plant level.

Options are:

ZB – Active material (Fully setup for Replenishment)

ZC – Depletion (End of Life, last orders have been issued)

ZD – Product Discontinued (Inventories have been depleted)

ZA – New Product Request (Creation of new SKU number in SAP)

ZP – Phase-in (Forecast and MRP are enable)

5. Planning time fence

  • Refers a period of time (in days) when there are no automatic changes to the master plan.

12. Period indicator

This field specifies the time period for which the consumption values are held for forecasting. The normal time period is one month (M).

5. Rounding value

  • Is the value to round in any requirement, the system will generate requirement in multiples of the given value.
  • Example: If the requirement is for 70 units and the rounding value is 20, the system will generate a planned order for 80 units

6. Rounding value

  • Is the value to round in any requirement, the system will generate requirement in multiples of the given value.
  • Example: If the requirement is for 70 units and the rounding value is 20, the system will generate a planned order for 80 units

4. Planning time fence

  • Refers a period of time (in days) when there are no automatic changes to the master plan.

8. Special procurement

This field helps to define any special procurement process involved in the procurement of the material. The special procurement type is only set on the receiving plant.

4. Lot size

Determines the procedure to calculates the reorder quantity in the planning run.

a) Static lot sizes

Determines a static lot sizing. The most common options are:

EX – Any requirement will trigger the exact quantity to be produced or purchased

FX and HB – not used in Becle

b) Lot sizes by period procedure

SAP will consolidate the requirements in a given period and manage them as the batch size to be produced or purchased. The most common options are:

WB – Weekly lot size

W6 – 42 days lot size

W2 – 14 days lot size

W9 – 60 days lot size

W3 – 21 days lot size

WQ – 91 days lot size

W4 – 28 days lot size

YS – 180 days lot size

1. MRP Type

Defines how the materials is planned, according to the following options:

Options are:

PD – Standard MRP, is used for materials included in a BOM

ND – No planning

M0 – MPS fixing type

M3 – MPS with planning time fence

2. MRP Type

Defines how the materials is planned, according to the following options:

Options are:

PD – Standard MRP, is used for materials included in a BOM

ND – No planning

M0 – MPS fixing type

M3 – MPS with planning time fence

7. Planned Delivery Time

Describes the average time it takes for a material to be delivered from the vendor

You can use transaction code MM02 or you need to follow the menu path:

Materials Master

SAP Easy Access

SAP Menu

Material

Logistics

Change

Immediately (MM02)

Materials Management

11. Coverage profile

This field defines parameters used in the calculation of dynamic safety stock. The dynamic safety stock is calculated using daily average requirements and the range of coverage.

8. Coverage profile

  • This field defines parameters used in the calculation of dynamic safety stock.
  • The dynamic safety stock is calculated using daily average requirements and the range of coverage.

2. MRP Controller

Reflects a person who is responsible for the planning of the material in one plant or company. Any planned material should be assigned to a MRP controller. Standard SAP reports will filter materials and results based on MRP controllers.

9. Period indicator

This field specifies the time period for which the consumption values are held for forecasting. The normal time period is one month (M).

10. Planned Delivery Time

Describes the average time it takes for a material to be delivered from the vendor.

7. Procurement type

Describes how a material is procured. The material can be purchased externally from a vendor, be produced in-house via a production order, or be both produced and purchased.

Options are:

E = Internally produced (manufactured in-house).

F = External procurement, purchasing process.

X = Both internal and external procurement are possible (not commonly used in Becle).