Want to create interactive content? It’s easy in Genially!
The Site Safety Manager: A Day in the Field
George Villalobos
Created on October 24, 2025
Start designing with a free template
Discover more than 1500 professional designs like these:
View
Corporate Escape Room: Operation Christmas
View
Secret Code
View
Reboot Protocol
View
Christmas Escape Room
View
Horror Escape Room
View
Witchcraft Escape Room
View
Desert Island Escape
Transcript
The Site Safety Manager: A Day in the Field
Test Your Skills, Crack the Codes
start
Introduction
Welcome to “The Site Safety Manager: A Day In The Field”.
You are the Site Safety Manager on a high-profile NYC construction project. The site is active, deadlines are tight, and safety cannot be compromised. Suddenly, hazards emerge: an unsecured sidewalk shed, incomplete fire protection, and a tower crane ready to operate without inspection. Your mission is clear: navigate three escalating levels of challenges, crack the codes for the day. ⚠️ Important: Every answer matters. You must answer every question correctly to progress. One mistake, and you will restart the level. Only by mastering all challenges will you secure the site.
Are you ready?
Start
Ground Level
Complete each level to complete the challenge
Level 1
Level 2
Level 3
Level 1
2/3
You Ask yourself...
"When must a sidewalk shed be inspected and approved by the DOB?"
Only after it has been in place for 30 days
Before it is used to protect pedestrians, after installation
Only if work above 40 feet requires it
Level 1
1/3
What should you do first?
Under the sidewalk shed, you notice several loose planks and misaligned scaffolding. Pedestrians are walking nearby. You recall NYC Building Code Chapter 33, Section 3309, which requires sidewalk sheds to be safe and properly maintained.
Notify the contractor immediately and write it in your report
Rope off the area and notify the contractor immediately
Level 1
3/3
Stop, tag it as non-compliant, and notify the responsible crew immediately.
What do you do?
You decide to walk up the stairs to the top floor of the site. You notice a fire extinguisher is missing its inspection tag.
Notify the local fire department
Replace it at the end of the day.
Ignore it; it’s probably fine.
Level 2
Complete each level to complete the challenge
Level 2
Level 1
Level 3
Level 2
1/3
What should you do?
Crane Log
After addressing the sidewalk shed, you walk over to observe the crane delivering steel beams to the upper floors. You notice the crane operator’s daily inspection log hasn’t been filled out for the day, and there are no warning signs posted for pedestrians below.You recall NYC Building Code Chapter 3310, which requires that all cranes must have a completed daily inspection log, proper safety signage, and barriers to protect pedestrians before operation.
Stop work in the affected area and ensure inspection is completed and proper signage posted.
Wait until the final crane pick and notify the crane operator and rigging crew.
2/3
Level 2
Do not allow the rigger to participate in the lift until a valid certification is provided
What should you do?
You approach the rigging crew before they start the lift and ask to see their certifications. Four riggers present their credentials, but you notice that one rigger’s certification has expired.
Let the rigger work for this lift and remind them to renew their certification later
3/3
Level 2
What should you do first?
You look to the side and notice a scaffold platform missing a mid-rail, with workers standing on it.
Call the competent person
Stop work on the scaffold and ensure proper guardrails are installed
Level 3
Complete each level to complete the challenge
Level 1
Level 2
Level 3
Level 3
1/3
Is the statement True or False?
A worker tells you: “I have my 4-Hour scaffold user card, that means I can erect this scaffold."
True
False
Level 3
2/3
Select a response
You go to your office and a project manager asks, “Can we skip the temporary fire watch tonight since the sprinklers are almost fully connected?”
Sure!
Absolutely not
Level 3
3/3
What should you do before leaving for the day?
It's the end of a long day, you are performing your final site walkthrough. You notice several tools and materials left unsecured on elevated platforms.
Ensure all tools and materials are properly secured, cordoned off if necessary, and document the actions in your site log before leaving.
Leave the site as scheduled, assuming workers will secure everything tomorrow.
Level 1
Level 3
Level 2
Completed!
Remember, when you get your license, integrity and good moral character matter as much as technical knowledge. Stay vigilant, document accurately, and let every decision on site reflect professionalism and responsibility.
Start over?
Oh oh!
That answer is not correct...
But don't lose your balance, continue on your way and try again!
back
Chapter 33 – §3309.2.1 & §3309.2.2:
Midrails: Must be installed on open sides of scaffolds, platforms, or elevated work surfaces between the top rail and the working surface to prevent falls. Toeboards: Required along the edges of platforms where there is a risk of tools or materials falling, at least 4 inches high, to protect workers below. Purpose: Prevent workers from falling and stop tools or debris from dropping onto people or property below.
