OEE: OVERALL EQUIPMENT EFFICICIENCY

GILEN SANTISO IRUSTA

Created on March 24, 2025

Start designing with a free template

Discover more than 1500 professional designs like these:

Akihabara Connectors Infographic

Essential Infographic

Practical Infographic

Akihabara Infographic

Interactive QR Code Generator

Witchcraft vertical Infographic

Halloween Horizontal Infographic

Transcript

OEE: OVERALL EQUIPMENT EFFICICIENCY

RENDIMIENTO

+info

+info

CALIDAD

OEE

+info

DISPONIBILIDAD

Tiempo de carga (100%)

OEE_FORMULA © 2025 by Gilen Santiso Irusta under CC BY-NC-SA 4.0

Netiket@ arauak FA. © 2025 by Gilen Santiso Irusta under CC BY-NC-SA 4.0
Netiket@ arauak FA. © 2025 by Gilen Santiso Irusta under CC BY-NC-SA 4.0
Netiket@ arauak FA. © 2025 by Gilen Santiso Irusta under CC BY-NC-SA 4.0

Definición: Eficiencia general de los equipos

Ejemplo >

Definición

Calidad = Tiempo útil (Parte proporcional de piezas buenas eliminando los rechazos)

Ejemplo > Datos

  • Ha habido 21 piezas rechazadas de todas las producidas

Definición:

Disponibilidad = Utilización = Tiempo de carga - Paradas no planificadas

Ejemplo > Datos

  • Parada por avería polea 20min
  • Parada por falta de material 10 min

Definición:

Rendimiento = Tiempo neto / Tiempo en funcionamiento Tiempo que deberíamos haber utilizado para realizar N piezas. Está relacionado con el tiempo de ciclo ideal. Si se incluyen las microparadas o hay una reducción de velocidad o ritmo de producción, el rendimiento disminuye

  • Cadencia ideal de producción 45 piezas /dia
  • Piezas producidas 300

Ejemplo > Datos

Definiciones:

Tiempo que esta en disposición de fabricar= Tiempo planificado para producir Paradas planificadas se excluyen (Ej: Reunión diaria)

Ejemplo:

  • 1 Turno = 8 Horas (No hay paradas planificadas)
Tiempo de carga = (8 x 60) = 480 minutos