Want to create interactive content? It’s easy in Genially!

Get started free

SPP Interconnection Checklist

Mary Muldrow

Created on January 29, 2024

Start designing with a free template

Discover more than 1500 professional designs like these:

Smart Presentation

Practical Presentation

Essential Presentation

Akihabara Presentation

Pastel Color Presentation

Visual Presentation

Relaxing Presentation

Transcript

SPP's Interconnection Checklist

Start

Click each sticky pad to reveal the contents.

Interconnection Checklist
Step 1

Trained personnel are on site (power plants and substations) to perform/assist with synchronization efforts.

Lines 1-9 of the checklist are completed by the RC in Step 1.

Reliable communications have been established and contact information shared with affected parties
Interconnection Checklist
Step 2

Click the blank notebook to reveal the contents.

We evaluate the stability of the existing islands in Step 2.Information is considered for two islands in Lines 10-21.

Knowlege Check

Line 10

Click each box to reveal the value. Then, answer the question that follows.

59.96

59.95

YES
Are both islands' frequencies within the preferred range?
NO

Click each box to reveal the contents.

Application Question

Calculation Review

Formula for % difference

For example, for voltages values of 353 kV and 344 kV:Step 1: 353-344=9 Step 2: 353+344=697; 697/2=348.5 Step 3: 9/348.5=0.0258; 0.0258*100=2.58% All: [353 kV – 344 kV] / ((353 kV + 344 kV) / 2) = 0.0258 * 100 = 2.58%

Line 11

Click each box to reveal the value. Then, answer the question that follows.

115.9

109

YES
Is the voltage difference within the preferred range?
NO

The next lines deal with Capability, Output, and Total Unloaded Capacity

Let's see what you already know

Click the top to view your question

Click each box to reveal the contents.

Challenge Question

Total Unloaded Capacity

Fleet Capacity MW - Fleet's Actual MW
= Total Unloaded Capacity

Lines 12-14

Click each box to reveal the value.

795

3580

1522

306

Then, drag and drop the correct values into the corresponding boxes

489 MW

2058MW

1842 MW

2058MW

489 MW
Check my answer

Lines 15-18

Holcomb 1

Tolk

Click each box to reveal the value.

500

360

Then, drag and drop the correct values into the corresponding boxes

239

200

121 MW
300 MW

61 MW

300MW

121 MW
Check my answer

Challenge Questions

Click the top of each box to reveal the questions.

Challenge Question

Click the top of the box to reveal the question.

Lines 19-21

Click each box to reveal the value.

73

351

Then, drag and drop the correct values into the corresponding boxes

351 MW

73 Mw

161 MW

Challenge Questions

Click the top of each box to reveal the questions.

Click each box to reveal the contents.

Interconnection Checklist
Step 3

We EVALUATE THE INTERCONNECT in Step 3.This is completed in Lines 22-28.

Lines 22-28

Click each box to reveal the value.

CB3707 at Liberal_

TBD
Yes
No
Tolk
SECI=FT; SPS=FF
Yes
Interconnection Checklist
Step 4

We evaluate the RESULTING ISLAND in Step 4.This is completed in Lines 29-37.

Lines 29-34

Click each box to reveal the value.

4375
2547
Holcomb at 239
485
485

Lines 35-37

Click each number to reveal the line.

Verify total dynamic reserve (Line 34) equals or exceeds the largest contingency (Line 31). YES or NO

35

Balancing Areas must agree on scheduled interchange; flow should be maintained near zero if only one tie line.

36

As islands grow, AGC modes, reserves, tie line flows, etc. need to be reviewed with all Balancing Authorities, Transmission Operators, and Balancing Authorities (if control has been transferred back to the Balancing Authority).

37

Interconnection Checklist

Click the index card to reveal the contents.

Step 5

Step 5 is the RC's approval of the interconnection.This is completed on Line 38.

Lines 39-42

Click each number to reveal the line.

Additional Notes

39

Establish additional tie lines as soon as possible.
Each entity should not pick up more than 5% of online capacity without notification to the RC.

40

Balancing Authorities shall agree on scheduled interchange; flow should be maintained near zero if only one tie line.

41

As islands grow, AGC modes, reserves, tie line flows, etc. need to be reviewed with all island Transmission Operators periodically.

42

The End