Want to create interactive content? It’s easy in Genially!
SPP Interconnection Checklist
Mary Muldrow
Created on January 29, 2024
Start designing with a free template
Discover more than 1500 professional designs like these:
View
Smart Presentation
View
Practical Presentation
View
Essential Presentation
View
Akihabara Presentation
View
Pastel Color Presentation
View
Visual Presentation
View
Relaxing Presentation
Transcript
SPP's Interconnection Checklist
Start
Click each sticky pad to reveal the contents.
Interconnection Checklist
Step 1
Trained personnel are on site (power plants and substations) to perform/assist with synchronization efforts.
Lines 1-9 of the checklist are completed by the RC in Step 1.
Reliable communications have been established and contact information shared with affected parties
Interconnection Checklist
Step 2
Click the blank notebook to reveal the contents.
We evaluate the stability of the existing islands in Step 2.Information is considered for two islands in Lines 10-21.
Knowlege Check
Line 10
Click each box to reveal the value. Then, answer the question that follows.
59.96
59.95
YES
Are both islands' frequencies within the preferred range?
NO
Click each box to reveal the contents.
Application Question
Calculation Review
Formula for % difference
For example, for voltages values of 353 kV and 344 kV:Step 1: 353-344=9 Step 2: 353+344=697; 697/2=348.5 Step 3: 9/348.5=0.0258; 0.0258*100=2.58% All: [353 kV – 344 kV] / ((353 kV + 344 kV) / 2) = 0.0258 * 100 = 2.58%
Line 11
Click each box to reveal the value. Then, answer the question that follows.
115.9
109
YES
Is the voltage difference within the preferred range?
NO
The next lines deal with Capability, Output, and Total Unloaded Capacity
Let's see what you already know
Click the top to view your question
Click each box to reveal the contents.
Challenge Question
Total Unloaded Capacity
Fleet Capacity MW - Fleet's Actual MW
= Total Unloaded Capacity
Lines 12-14
Click each box to reveal the value.
795
3580
1522
306
Then, drag and drop the correct values into the corresponding boxes
489 MW
2058MW
1842 MW
2058MW
489 MW
Check my answer
Lines 15-18
Holcomb 1
Tolk
Click each box to reveal the value.
500
360
Then, drag and drop the correct values into the corresponding boxes
239
200
121 MW
300 MW
61 MW
300MW
121 MW
Check my answer
Challenge Questions
Click the top of each box to reveal the questions.
Challenge Question
Click the top of the box to reveal the question.
Lines 19-21
Click each box to reveal the value.
73
351
Then, drag and drop the correct values into the corresponding boxes
351 MW
73 Mw
161 MW
Challenge Questions
Click the top of each box to reveal the questions.
Click each box to reveal the contents.
Interconnection Checklist
Step 3
We EVALUATE THE INTERCONNECT in Step 3.This is completed in Lines 22-28.
Lines 22-28
Click each box to reveal the value.
CB3707 at Liberal_
TBD
Yes
No
Tolk
SECI=FT; SPS=FF
Yes
Interconnection Checklist
Step 4
We evaluate the RESULTING ISLAND in Step 4.This is completed in Lines 29-37.
Lines 29-34
Click each box to reveal the value.
4375
2547
Holcomb at 239
485
485
Lines 35-37
Click each number to reveal the line.
Verify total dynamic reserve (Line 34) equals or exceeds the largest contingency (Line 31). YES or NO
35
Balancing Areas must agree on scheduled interchange; flow should be maintained near zero if only one tie line.
36
As islands grow, AGC modes, reserves, tie line flows, etc. need to be reviewed with all Balancing Authorities, Transmission Operators, and Balancing Authorities (if control has been transferred back to the Balancing Authority).
37
Interconnection Checklist
Click the index card to reveal the contents.
Step 5
Step 5 is the RC's approval of the interconnection.This is completed on Line 38.
Lines 39-42
Click each number to reveal the line.
Additional Notes
39
Establish additional tie lines as soon as possible.
Each entity should not pick up more than 5% of online capacity without notification to the RC.
40
Balancing Authorities shall agree on scheduled interchange; flow should be maintained near zero if only one tie line.
41
As islands grow, AGC modes, reserves, tie line flows, etc. need to be reviewed with all island Transmission Operators periodically.
42
The End