Phase 1
Phase 2
Phase 3
Phase 4
% Progress
Phase 1100
Phase 290.69
Phase 353.86
Phase 419.78
Chart data table
District Construction and Renovations
High School 
New Construction
CTE Building 
Phase 4
19.78% Complete
Elementary Schools
Outdoor Basketball Courts, Outdoor Learning Center, Playgrounds (ADA Complaint) & Playground Canopies, Walking Trails

Junior High
Walking Trail, Outdoor Learning Center

High School
Walking Trail, Outdoor Learning Center
Phase 3
53.86% Complete
Derry and Garriga

Restrooms 
Phase 1
100 % Complete
All Campuses 

Staff Lounge/Restrooms

High School
Auditorium

Junior High 
Locker room, Stage, Life Skills Classroom
Phase 2
90.69% Complete

Want to create interactive content? It’s easy in Genially!

Get started free

Point Isabel ISD District Construction and Renovations

Juliette Gonzalez-Ba

Created on September 26, 2023

Start designing with a free template

Discover more than 1500 professional designs like these:

Transcript

District Construction and Renovations

High School New Construction CTE Building

Phase 4

19.78% Complete

Elementary Schools Outdoor Basketball Courts, Outdoor Learning Center, Playgrounds (ADA Complaint) & Playground Canopies, Walking Trails Junior High Walking Trail, Outdoor Learning Center High School Walking Trail, Outdoor Learning Center

Phase 3

53.86% Complete

Derry and Garriga Restrooms

Phase 1

100 % Complete

All Campuses Staff Lounge/Restrooms High School Auditorium Junior High Locker room, Stage, Life Skills Classroom

Phase 2

90.69% Complete

Progress

Elementary Schools –Outdoor Basketball Courts, Outdoor Learning Center, Playgrounds (ADA Compliant)& Playground Canopies, Walking Trails Jr High – Walking trail, Outdoor Learning Center High School – Walking trail, Transition Learning Center (located at Jr High) Notice to Proceed – June 20, 2023 Days to complete: 240 calendar days Substantial Completion Date: February 21, 2024

Start Date: January 2023 Completion Date: August 2023

Phase 3

Gallery

Info

+info

Progress

Derry & Garriga Student Restrooms Needs more data

Start Date: January 2023 Completion Date: August 2023

Phase 1

Info

+info

Gallery

Progress

All Campuses - Staff Lounge/Restrooms High School- Auditorium Jr High - Locker Rooms, Stage, Life Skills Classroom

Notice to Proceed – Monday, April 3, 2023 Days to complete: 180 days Substantial Completion Date: September 30, 2023

Phase 2

Info

+info

Gallery

Progress

Phase 4 – New Construction Project: CTE Building

Notice to Proceed – June 20, 2023 Days to complete: 365 Calendar Days Substantial Completion Date: June 25, 2024