What does the environmental protection permit process involve?

we check whether the application is correct and, if necessary, ask to eliminate any deficiencies

the authorisation procedure is suspended for the duration of the assessment

if necessary, we initiate an environmental impact assessment

submission of application

up to 21 days

we prepare a draft permit for granting or refusing permission

we issue or refuse an environmental protection permit

we consider the need for an environmental impact assessment

we accept the application

from the acceptance of the application to decision it will take: environmental permit up to 90 days, integrated permit (IED based) up to 180 days,mining permit up to 1 year

we inform the public about the submission of the application

we inform the public and, if necessary, arrange public discussion

we inform the public

we ask the opinion of the local government

we ask the opinion of the local government

at least 14 days

at least 14 days

at least 30 days

at least 14 days